Northamptonshire Case Study
An example of an upgraded backup generator system
Background
- Site visit to understand the scope of the work necessary.
- Old analogue system that was difficult to maintain.
- Wasn’t fit for purpose
- Full of risk
- Obsolete parts
- Didn’t have good process visibility in the way of alarms or events
Tailored Specification
- Make use of the existing containerised engine and alternator but with new control system integrated into the existing LV distribution system.
- Factory Acceptance Test (FAT) showing all the control functions and full cause and effect of the entire integrated system.
- New control cabinets for all three generators and LV network changeover systems.
Installation
Carried out with no disruption to the business by scheduling the work in a time efficient and flexible manner.